Physics (AS & A Level) · Feb / March 2025 · Paper 12 · Question 17
A turbine at a hydroelectric power station is situated at a vertical distance of 30 m below the level of the surface of a large lake. The water passes through the turbine at a rate of 340 m³ per minute. The overall efficiency of the turbine and generator system is 90%. The density of water is 1000 kg m⁻³. What is the useful power output of the power station?
- A0.15 MW
- B1.5 MW
- C1.7 MW
- D90 MW
As printed in the paper
Show the answer
Correct answer: B. 1.5 MW