Economics (AS & A Level) · May / June 2025 · Paper 34 · Question 4
9708Private costs and benefits, externalities and social costs and benefits
A cost–benefit analysis is carried out on the construction of a hydroelectric power station. Under which circumstances would the scheme be most likely to be approved?
- APrivate benefits are greater than private costs.
- BSocial benefits are greater than social costs.
- CSocial benefits are greater than external costs.
- DExternal costs are greater than external benefits.
As printed in the paper
Show the answer
Correct answer: B. Social benefits are greater than social costs.