Economics (AS & A Level) · Feb / March 2023 · Paper 32 · Question 9
9708Private costs and benefits, externalities and social costs and benefits
The result of a cost-benefit analysis of a proposed government road-building project is that there will be a positive net social benefit of $50 million. Why might the government not proceed with the project?
- AThe project would not be profitable for a private firm.
- BThe project would cause negative externalities.
- CThere is limited capital available for government projects.
- DThere would be more who lost than gained.
As printed in the paper
Show the answer
Correct answer: C. There is limited capital available for government projects.