Economics (AS & A Level) · Oct / Nov 2021 · Paper 32 · Question 3

9708Private costs and benefits, externalities and social costs and benefits

A government uses a cost–benefit analysis approach to infrastructure projects. It is considering building a new railway to link a city centre to its airport. It estimates the following. private costs 1.0; social costs 1.7; private benefits 0.5; external benefits 1.8 ($ billion) What should the government decide and why?

  1. Ado not proceed; total costs exceed external benefits
  2. Bdo not proceed; total costs exceed total benefits
  3. Cproceed; private costs exceed private benefits
  4. Dproceed; social benefits exceed social costs

As printed in the paper

Show the answer

Correct answer: D. proceed; social benefits exceed social costs